The project is developed by Sagajuta Sabah Sdn Bhd, and predicted to be completed in 2015.
[1] However, due to several issues, the building remained unfinished until 2016, leading to the developer being sued by property lots buyers as well as from the Malaysian Inland Revenue Board.
[2] On 24 November 2016, the project was officially declared abandoned by the Ministry of Local Government.
[citation needed] On 21 June 2016, the Malaysian Inland Revenue Board sued the developer over its failure to settle its tax arrears totalling over RM8.5 million.
[4][5] The project was subsequently undertaken by UHY Advisory (KL) Sdn Bhd on 15 January 2018 as stated in the website of Sabah Ministry of Local Government and Housing,[6] although further rescue proposed scheme by court requesting the buyers to paid an additional RM130 per square foot to Excel Glamour Housing Sdn Bhd to complete the final 20% of the project has drawn objections since the firm was appointed without any open tender as well the way the company seems to be profiting from the problem.