Arlanda Line

It is built for speeds of 200 kilometres per hour (120 mph), is electrified at 15 kV  16.7 Hz AC and is double track.

The private consortium was granted a 40-year permit to operate the line in exchange for all direct traffic and the right to collect usage fees from other train companies.

The goal was to reduce road congestion and emissions while allowing Arlanda to keep increasing passenger numbers.

The Swedish Rail Administration made a specific plan in the late 1980s which involved the construction of a branch from the existing East Coast Line.

This resulted in a project plan which was launched in 1990, which specifically suggested Rosersberg and Odensala as the intersections with the existing line.

[9] The Swedish Rail Administration had proposed that the line was to be built with the government agency as owner and with either SJ or private railway companies as train operators.

In 1994, Arlanda Link Consortium was chosen, consisting of the Nordic Construction Company, SIAB [sv], Vattenfall, GEC-Alsthom and Mowlem.

[8] The company was also allowed to operate a shuttle service from Stockholm C to Arlanda and charge a non-discriminating fee for all other trains using the line.

The public–private partnership part of the project involved two new tracks at Stockholm C and the Arlanda Line, costing SEK 4.1 billion.

A-Train was also granted an interest-free deferral on the payment of the fees at Stockholm C and Arlanda, costing the state SEK 90 million.

It also criticized the Government for giving additional financial support to A-Train in the form of guarantees without informing the Riksdag, and having an unclear management strategy.

However, because A-Train is free to set its ticket prices as it wishes, the high prices resulted in too few passengers taking the Arlanda Line for it to be of economic benefit to the Swedish community, and the line failed to maximise its economic impact through reduced road congestion and emissions.

[15][16] The Swedish State holds an option to purchase the traffic rights from A-Train in 2010, which would eliminate the fees and allow other operators to run directly from the airport to the city center.

Commentators and politicians have stated that the business model results in a low utilization of the line because of the high ticket prices, which has caused the airport to not reach its targeted emission goals.

Entrance to Arlanda Central Station from the airport
X3 on the East Coast Line