[4][5][6] The company built its first cement plant in Hattar, in the Khyber Pakhtoonkhwa in 1995 with an initial investment of US$120 million.
Civil works for Bestway Chakwal-I were initiated in January 2005, the kiln was fired in May 2006 and the plant went into production in June 2006.
The local people claim that Bestway Group did not fairly compensate the previous owners of the land.
[8][9] In September 2005, Bestway bid for 85.29% of the equity of Mustehkam Cement Limited under the Privatization Scheme and acquired the company for $70.0 million.
[20] In March 2017, Bestway announced plans to set up its third cement plant in Haripur KPK Province.
[23][24] In June 2021, Bestway commissioned its first 14.3MW captive solar power unit at its integrated cement plant at Farooqia, Khyber Pakhtunkhwa.