[2] As it is situated in an earthquake-prone area it is India's first bridge to have fully welded steel-concrete support beams that can withstand earthquakes of magnitudes up to 7 on the Richter scale.
It was inaugurated by Prime Minister Narendra Modi on 25 December 2018 on the occasion of Good Governance Day.
[8] The bridge is located just over 20 km away from the Assam- Arunachal Pradesh border and acts as an alternative to the Kolia Bhomora Setu, Tezpur in providing connectivity to nearly five million people residing in Upper Assam and Arunachal Pradesh.
[9] A New Dibrugarh Railway Station, expected to be the largest in the region, has been proposed and is to be linked to the Rangiya–Murkongselek line via Chaulkhowa and Moranhat.
[14] The project was to be completed in six years following the inauguration, however the work did not begin even in 2007, owing to lack of funds and attention.
[16] In April 2008, the Northeast Frontier Railway contracted Gammon India to construct the sub-structure of the bridge while a consortium of Hindustan Construction Company, DSD Brückenbau GmbH, Germany and VNR Infrastructures won the bid to build the superstructure.
[18][19] According to a press release by the Indian Ministry of Railway on 25 July 2014, in the main bridge 36 out of 42 well foundations and 28 out of 40 piers had been completed, while 2 out of 41 girders had been launched.
[20] However, a correspondent writing in The Hindu Business Line claimed that when he visited the project in July 2014, only 15 out of the 42 piers were "coming up", while the work on the rest had barely begun.
[22] The design of the bridge has 41 spans of 125 m and a superstructure of composite welded steel truss and reinforced concrete.