Butibori Power Plant

The Engineering, procurement and construction contract is given to Reliance Infrastructure and Shanghai Electric Corporation of People's Republic of China is supplying the boiler, turbine and generator (BTG) for the power plant.

[1] Along with Power generation units, there are two reservoirs of water, one of which has intake from the MIDC area and the other from the nearby Wadgaon dam.

It is crushed to 20 mm and then put into a coal mill, which pulverizes it into extremely fine powder of around 70 microns.

The turbines run at a constant speed of 3000 rpm, so as to provide a steady output of 50 Hz.

Post combustion, the mixture of flue gases and ash passes over an Electrostatic Precipitator (ESP).

This attracts the ash particles, which are usually positively or negatively charged, to its surface and lets the uncharged flue gases through to the chimneys.

Chemicals used in the Water treatment plant are Lime Dolomite, Poly electrolyte, Chlorine gas, SMBS (Sodium metabisulphate) and an antiscalant.