Canada Dock Branch

The initial stations were: Canada Dock, Walton & Anfield, Breck Road, Tue Brook, Stanley and Edge Lane.

[3] During 2021, work took place to double the 400 metres of single line section of the track, allowing trains greater flexibility to enter and exit the mainline.

The Olive Mount chord at Edge Hill junction was re-opened in December 2008, approximately doubling the Canada Dock branch's throughput of freight from the Port of Liverpool to the West Coast Main Line.

The reinstatement of the chord was essential for existing port operations, ready for the increase in freight when the Post-Panamax, Liverpool2 container terminal was completed at Seaforth Dock.

Biomass wood pellets are imported into Liverpool and delivered to the Drax power station in Yorkshire via the rail link.

[9] The October 2017 Liverpool City Region Combined Authority update to the Long Term Rail Strategy mentions the re-opening of the line to passenger use with new stations at Anfield, Tue Brook and Edge Lane.

[11] It was announced in December 2019 that Liverpool City Council had commissioned a feasibility study to see about reopening the Canada Dock Branch to passenger traffic.