The station has four island platforms and eight tracks, and consists of three floors connected by footbridges.
The predecessor Chiryū Station was opened on April 1, 1923, as Shin Chiryū Station (新知立駅, Shin-Chiryū-eki) on the privately owned Aichi Electric Railway Company, but soon merged with nearby Chiryū Station (知立駅, Chiryū-eki) on the Mikawa Railway later that year.
[1] Originally scheduled for a 2023 completion, the completion date has been pushed back to 2028 while the price of the project has increased to ¥79 billion (2021) (US$722 million) from its original cost of ¥61 billion (US$556 million).
[1] The tracks for each of the lines will gradually be moved to the new station structure.
[1] The first tracks that were moved to the new facilities were the southbound tracks on the Nagoya Main Line (previously serving platform 6), which were reassigned to platform 8 on the new elevated level on 21 March 2023.