East Klang Valley Expressway

The 39.5-kilometre-long (24.5 mi) expressway will connect Ukay Perdana in Ampang, Selangor and Bandar Sungai Long in Kajang.

[2] The expressways for phase 1 starts from Kuala Lumpur Middle Ring Road 2 in Ukay Perdana (north), Ulu Klang, via Ampang, Hulu Langat, Bandar Mahkota Cheras ending at Kajang Dispersal Link in Sungai Long (south).

EKVE Sdn Bhd (a member of Ahmad Zaki Resources Berhad (AZRB)), the developer of the expressway, is expected to begin construction of the RM 1.55 billion project in September 2015.

[4] However, due to several lawsuit against EKVE Sdn Bhd involving a piece of land at Beverly Heights, the completion of the highway were delayed to 2023 as per announced by then Minister of Works, Fadillah Yusof in October 2022.

[5] The expected completion and opening were further delayed to 2024, when then new Minister of Works Alexander Nanta Linggi stated in a written parliamentary reply in March 2023 that the delay were caused by halting of works due to rising costs of construction.

View of East Klang Valley Expressway in Ukay Perdana, Selangor