[8][9] For much of its existence the line has played a minor role in London's transport system; however, in recent years it has received significant investment to increase its capacity, including full 25kV AC overhead electrification, completed in 2018.
[10] At the eastern end of the line, the extension to the Barking Riverside regeneration site opened on 18 July 2022.
[citation needed] Although the route between Upper Holloway and Woodgrange Park has been constant, several stations have been the ends of the line.
Even so, it was allowed to fall into a poor state of repair and reliability,[14] and by 1980 had been cut back to an hourly service between Kentish Town and Barking.
The Railways Act 2005 abolished the franchise and gave the operation of passenger services to Transport for London (TfL).
During 2005, TfL started funding a small number of additional peak time and late evening services to relieve the worst overcrowding.
[citation needed] In November 2007, TfL took full control of the line, after which it introduced improved late night and weekend services, and staff, ticket machines and Oyster equipment at all stations.
The frequency was increased to three trains per hour during morning and afternoon peaks and the line was included on the Tube map for the first time.
By replacing the overbridges carrying Sussex Way and Albert Road, and lowering the track in some other locations, it was made possible for W10 loading gauge goods trains to operate.
[21] In August, the Mayor wrote to the Secretary of State for Transport to seek a way forward, and "she committed her officials to support work with TfL, Network Rail, train operators and other industry parties to see if a viable way can be found to bridge the funding gap.
[23] In June 2013, it was announced that £115 million of funding for electrification would be made available as part of upgrades to rail infrastructure included in the government's 2013 spending round.
In February 2017, Network Rail announced that whilst the line would re-open as scheduled, they were not able to complete all the work planned due to "incorrect" designs and late delivery of materials.
However, the delivery of these trains was delayed by the manufacturer; at one point, officials were not even willing to divulge an anticipated service date for the Class 710 sets.
The two-coach Class 172 diesel trains in use between 2010 and 2019 were incapable of handling the increased number of passengers experienced after the incorporation into the London Overground.
[41] Running partially alongside the existing London, Tilbury and Southend Railway line and then a new viaduct to the Barking Riverside station, the extension opened to passengers on Monday 18 July 2022[42] at an estimated cost of £327m.
[43] On 23 January 2020, a freight wagon derailed between Leyton Midland Road and Walthamstow Queen's Road stations, causing extensive damage to more than 2.5 miles (4 km) of track; the line was closed between Barking and South Tottenham stations while repair works took place, whereby 10,000 tonnes of ballast, 5,300 concrete sleepers and 39 new pieces of rail were installed.
[49][50][51] There is a single weekday morning service from Woodgrange Park to Willesden Junction, calling at all intermediate stations except for Gospel Oak.
Passengers are required to buy tickets, or touch in with their Oyster or contactless cards, or else face a penalty fare.
Following the introduction of the current ticketing arrangements, ticketless travel fell from an estimated peak of 40% under Silverlink, to 2% in March 2008.
In 2017, all trains were diesel powered as the line was not fully electrified, with only two short sections having overhead electrification, at South Tottenham, to provide a link from Seven Sisters to Stratford, and from the junction with the Great Eastern Main Line to Barking but excluding the bay platform which this service uses.
[citation needed] Electrification of the line was completed in 2018, but electric trains did not run at first as the delivery of the new Class 710 sets had been delayed.
[66] As part of the extension to Barking Riverside, a station, called Castle Green, at Renwick Road on the London, Tilbury & Southend Railway was proposed.
[40] However, in 2019 Transport for London and City Hall proposed an extension of the Docklands Light Railway (DLR) to serve Thamesmead instead of an extension of the Overground, as part of the proposed Thamesmead and Abbey Wood OAPF (Opportunity Area Planning Framework).
Local residents and users of the line have proposed adding a station between Leytonstone High Road and Wanstead Park to serve the Cann Hall area.