Haibang station

[1] The Line 4 station started operations on 30 December 2006 and is located at the junction of Changnan Road.

The ceiling of the station adopts a gradient color wave shape, and the wall is decorated with watercolor wave patterns to show the local characteristics of the Shatian Water Town style.

[5] The project of the eastern extension of Line 3 was approved by the National Development and Reform Commission in late March 2017, and the construction report was approved in early January 2018,[6] followed by the construction of the station part of Line 3 in mid-2019.

[7] On 1 July 2023, the tunnel boring machine broke through, and on October 27, the main structure was topped out.

[17] However, it was not until October 30 that the Guangzhou Metro Group announced that the eastern extension of Line 3, including this station, would open on November 1 of the same year.