[3] Located on a 7,700m2 brownfield site in the Vauxhall district, bordering the northern edge of the city centre, the development is costing £250 million.
[2] Vermont started work on the foundations of Tower A in March 2019 using two rigs to drill concrete piles to a depth of 18 metres.
[20] However, in February 2022, the result of these legal challenges saw a judge rule in favour of a last minute bid from a consortium of investors – that the scheme should instead be sold to them instead.
[21] In autumn 2022, this group (comprising 213 of the 273 original investors) completed the takeover of the site, in a deal worth £5.9 million;[22] a Council report classified the project as a "stalled scheme currently not progressing".
[4] Amenities will include a spa, gym, swimming pool, cinema room, communal gardens, car parking, a lounge, meeting rooms and private dining, found on the floors below; the three towers are to be connected by an external 'podium' at second floor level to allow access to the facilities located in each block and is host to the garden space.