[9] The Jabodebek light rapid transit project is aimed to tackle Jakarta's high road traffic congestion.
Transportation experts deemed that the city center monorail project would not address Jakarta's traffic problems, but would only serve as a novelty tourists' ride.
[11] To answer the need for commuter infrastructure, a consortium of five state owned enterprises, led by PT Adhi Karya (previously part of the Jakarta Monorail consortium), proposed the construction of a 39.036 km (24.256 mi) monorail line connecting Cibubur-Cawang-Kuningan and Bekasi-Cawang across Greater Jakarta.
The numerous stalled monorail support poles will be used by state-owned construction company PT Adhi Karya to develop Jakarta's light rapid transit instead.
In 2015, it was announced that the Indonesian Cabinet Secretary has endorsed the plan to build three light rail transit lines.
The construction phase of extension for the planned route Grogol–Pesing–Rawa Buaya–Kamal Raya–Dadap–Soekarno–Hatta International Airport was proposed, but was not mentioned in the Presidential Regulation No.
[19] Construction of Phase 1 began on 9 September 2015 and was initially predicted to be operational by early 2018, in time for the 2018 Asian Games.
However, due to funding, restructuring and land acquisition issues, the project has failed to meet the deadline.
The LRT's public free trial run, similar to the Jakarta MRT, is planned started on 12 July 2023, with commercial operations slated to begin on 17 August 2023.