Article 54 of the project was significant in stating that any disagreement with property owners must be resolved by the Royal Court for consideration and decision, and the claimant could not cause work to cease by raising the clameur de haro (as had happened with the Jersey Railway construction).
On 15 May 1871, the committee appointed by the States met to consider objections by landowners; the majority were satisfied that they had received fair compensation.
The line was opened on 6 August 1873, with a train of six carriages taking the States Members and their wives along the track to Grouville Station in 15 minutes.
Most of the land was sold to adjacent landowners, but part of the route can be seen near Fauvic (at the southeastern tip of the island), where it has been preserved as a footpath.
[2] The Jersey Eastern Railway Terminus Hotel at Snow Hill remains, and is on the Register of Historic Buildings.