Keikyū Kamata Station (京急蒲田駅, Keikyū Kamata-eki) is a railway station in Ōta, Tokyo, Japan, operated by the private railway company Keikyu.
The 3rd floor consists of one large platform serving three tracks in a unique configuration.
[4] The station was rebuilt over a period of 12 years from December 2000 to October 2012 with the original ground-level tracks elevated to provide additional track capacity and eliminate road congestion on the three level crossings immediately adjacent to the station.
This would provide an interchange between the lines, improving accessibility to Tokyo's Haneda Airport ahead of the 2020 Summer Olympics.
As of June 2022[update], Ōta Ward has agreed with the Tokyo Metropolitan Government to pay 70% of the project cost of ¥136 billion (2021) (US$1.24 billion) while having the city government responsible for the remaining 30%.