Linth–Limmern Power Stations

Works on the complex began in 1957 with the construction of Lake Limmern Dam and the Mutt, Tierfehd and Linthal Power Stations.

Commissioning of the last unit in Limmern was completed by December 2017, bringing the total installed capacity of the system to 1480 MW.

Finally, the Linthal Balancing Reservoir is located down in the valley at an elevation of 676 m (2,218 ft) above sea level, and withholds 210,000 m3 (170 acre⋅ft) of water.

[3][7][4] Lake Limmern also provides water to the Tierfehd Power Station further down in the valley for conventional hydroelectric generation and pumped-storage.

Also in this Power Station, a 34 MW electrically driven pump allows the transfer of water from Hintersand Reservoir up to Lake Limmern.

The water in this reservoir can either be pumped back up to Lake Limmern or directed down to the Linthal Power Station, which has two 17.2 MW Pelton turbines.

Lake Mutt in 2006.