[4] The old structure was replaced with a completely new continuous truss which was constructed on temporary piers adjacent to the operational span between 2011 and 2012 and slid into place after demolition of the old span using a construction method called "truss sliding.
[2] As of 2009, one of the boons of the new bridge would be to aid a $20 million "resort and entertainment center" where a cotton mill once stood.
[10] The original bridge was removed except for several piers in the waterway, which were rehabilitated and widened to accommodate a new, wider steel-truss superstructure.
Passenger ferry service was provided by Madison-based Rockin Thunder Jet Boat Rides LLC during the bridge closure for the final slide.
In 15 days over 4000 passengers and 12 dogs were transported in a 6-passenger Jet Boat between Milton Kentucky and Madison Indiana.
On March 11, 2014, only four days before the truss slide was scheduled to begin, construction workers were installing a mechanism to facilitate the slide when a steel bearing on the southeast corner of the bridge dislodged, causing the bridge to drop by at least 1 foot (30 cm) and injuring one worker.
[12] Work was conducted to replace the steel bearing ten days later and the bridge opened to traffic at 7:20 PM on April 17, 2014.