[1] The road starts at Moroto and continues south through Lorengedwat, ending in Nakapiripirit, a distance of approximately 98 kilometres (61 mi).
[4] Beginning with the 2011/2012 national budget, road became one of those planned to be upgraded from gravel to bituminous surface.
With political pressure from the Karamoja parliamentary caucus, the road was prioritized in the 2013/2014 financial year.
[5] On 12 November 2013, President Yoweri Museveni commissioned the start of construction.
The China Road and Bridge Construction Corporation, a subsidiary of the China Communications Construction Company, was awarded the contract for the 93.3 kilometres (58 mi) road at a cost of US$80 million (USh:184 billion at that time), fully funded by the Ugandan government.