Musita–Mayuge–Lumino–Majanji–Busia Road

At Lumino, a southern spur, measuring about 8 kilometres (5 mi), goes south to Majanji on the northern shores of Lake Victoria.

[3] The main road makes a northerly turn to end at the border town of Busia (2014 population 55,958).

As described, including the spur to Majanji, the entire road project measures 104 kilometres (65 mi).

In February 2015, the Ugandan government began the process of upgrading the road to class II bitumen surface.

[8] In a letter dated 12 June 2017, UNRA Executive Director Allen Kagina canceled the contract, citing CR18's alleged incompetence, performance below contractual standards, lack of commitment to the project, and failure to mobilise resources and equipment to ensure timely completion of work.