[5][6][7][8] In 2013, four reactors were permanently closed: San Onofre 2 and 3 in California following equipment problems, Crystal River 3 in Florida, and Kewaunee in Wisconsin.
Summer was canceled due to delays and cost overruns[8] raising questions about the future of the two remaining US reactors under construction, since these are also of the AP1000 design.
[13] As of 2021, the private sector focus has shifted toward the development of small modular reactors (SMRs), which could theoretically cut down on the high costs and lengthy construction times of conventional nuclear plants.
[14] Both Presidents Donald Trump and Joe Biden have proposed or helped pass legislation that would increase subsidies for new and existing nuclear plants.
[26][27] In the wake of Fukushima, experts at the time saw continuing challenges that they felt would make it difficult for the nuclear power industry to expand beyond a small handful of reactor projects that "government agencies decide to subsidize by forcing taxpayers to assume the risk for the reactors and mandating that ratepayers pay for construction in advance".
[28] As of 2014, the U.S. nuclear industry began a new lobbying effort, hiring three former senators—Evan Bayh, a Democrat; Judd Gregg, a Republican; and Spencer Abraham, a Republican—as well as William M. Daley, a former staffer to President Obama.
[11] The U.S. government had given $8.3 billion of loan guarantees on the financing of the four nuclear reactors being built in the U.S., and it is expected a way forward to completing the plant can be agreed.
[31] As of 2017, the U.S. shale gas boom has lowered electricity generation costs placing severe pressure on the economics of operating older existing nuclear power plants.
[43] Both companies are developing small modular reactor (SMR) projects which are theoretically easier and more inexpensive to build than traditional plants.
[14] Similarly, the Energy Impact Center developed OPEN100, another SMR project introduced in 2020 that has published open-source blueprints for the design and construction of a nuclear power plant with a pressurized water reactor.
Toxic, radioactive waste (spent nuclear fuel) needs to be regularly removed from the reactors and disposed of safely for up to a million years, so that it does not pollute the environment.