The field was developed with a fixed production, drilling and quarters (PDQ) facility and is operated by Statoil.
The first stage phase processing is done at the Oseberg Øst platform.
The second and third phase processing of oil is done at the Oseberg Field Center and it is then transported to Sture terminal in Norway through the Oseberg Transport System.
[2] In the recent years, the facility has been modified and drilling of seven wells started.
[2] Partners developing the field invested NOK1.9 billion for upgrades and modifications in order to extract more oil from the field without the use of support vessels[3] and increase the recovery rate from 28 to 35%.