[4] At 4 o'clock in the morning on July 1, 2003, the Pudongnan Road-Nanpu Bridge section of Line 4 suddenly saw water seepage during the construction of the connecting passage between the upper and lower tunnels.
At 9 o'clock in the morning, the podium of a nearby building on South Zhongshan Road collapsed; beginning in the early morning of the July 2, the flood wall of Dongjiadu Waima Road section began to sink and crack due to the settlement.