[3] In 2011 Riga City Council terminated the agreement with Southern Bridge third round builders due to lack of funds.
[4] In early 2012 Riga City Council signed agreement with the new constructors to carry out final works of third stage of the Southern bridge and borrowed an additional seven million euros for funding.
[5] In 2009 The Economy Police launched a criminal case on suspected violations in construction of the bridge.
[6] State Audit Office concluded that the Riga City Council had squandered 27 million lats in the construction.
[7] In 2013 the students of Stockholm School of Economics in Riga calculated that the same bridge could've been built for a budget two times smaller.