The electrical connection to the 110 kV network, via two substations operated by e.dis AG, was made in April 2013.

It consists of 1.5 million thin-film modules from the manufacturer First Solar from its factory in Frankfurt (Oder).

The 114 power inverters used were supplied by German company SMA.

The construction costs were €204.5 million and about 500 people were employed during its fabrication.