[3] The railway originally ran from Bishop Auckland to Wearhead in County Durham, North-East England, a distance of 25 miles (40 km), built in the 19th century to carry limestone from Eastgate-in-Weardale, and provide passenger services to Weardale.
After completion of the Shildon tunnel, the BA&WR erected a permanent station on the current site, which opened to freight on 8 November 1843, and passengers on 30 January 1843.
[5][6] In July 1845 Parliament passed the Wear Valley Act, which allowed the extension of the BA&WR from a junction at Witton-le-Wear to Frosterley, and a small branch line across the river to Bishopley.
Between Eastgate and Westgate at Cambo Keels, sidings were established to serve the Weardale Iron Company's Heights limestone quarry, which is still in operation today.
The Weardale Railway preservation project was founded in 1993, with the intention that a private company should take ownership of the line and start a steam service for tourists on the scenic western section.
The Manpower Services Commission contributed to the wages of paid staff in what had become an area of high unemployment, and this allowed a 40-strong workforce to be recruited, a depot and base of operations to be established at Wolsingham and the station at Stanhope to be restored.
[14] In September 2008, Ealing Community Transport's 75% interest in WRC was transferred to British American Railway Services, a wholly owned subsidiary of US private company Iowa Pacific Holdings.
[15][16] Ed Ellis, the spokesman for these firms, visited the Weardale Railway in October 2008, and announced an intention to reopen the line to Bishop Auckland by the end of 2008.
In October 2008, the line's paid staff and volunteers undertook the "Brush Blitz" to clear 14 years of vegetation growth from the track between Wolsingham and Bishop Auckland.
[17] After two damaged sections of track were repaired, in early 2009 a passenger-carrying Wickham trolley (light rail vehicle) was able to negotiate the line from Wolsingham to within sight of Bishop Auckland station.
[20] On 29 September 2009, the development of the Eastgate Renewable Energy Village received unanimous outline approval by the County Durham strategic planning committee, thus providing a potential boost to the line's future prospects.
[24] On 25 January 2010, Her Majesty's Railway Inspectorate travelled on the Weardale line checking bridges, fences and crossings along the 18-mile stretch between Stanhope and Bishop Auckland.
Only a few minor works were needed to get the line ready for passenger use, and these were completed in time for a London King's Cross to Stanhope charter train to run.
[28] In April 2018, the Weardale Railway CIC announced that works had commenced to lift a short section of track at Broken Banks (approximately 1⁄2 mile (800 m) west of Bishop Auckland) to enable the embankment to be repaired after subsidence had made the line unusable for passenger traffic.
Once the works were completed it was intended to reinstate the tracks and extend the Stanhope to Witton-le-Wear passenger service back to Bishop Auckland West station.