West of Duddon Sands Wind Farm

The wind farm gets its name from a large sand bank uncovered at low water in the mouth of the estuary of the River Duddon to the north of the Furness Peninsula.

The farm actually lies to the south west of the Duddon Sands and covers an area of approximately 67 km2.

[3] The project was awarded to Morecambe Wind Ltd, a partnership between Scottish Power, Elsam, and Eurus Energy.

[4] The project included constructing the wind turbines and their foundations, building offshore substations, installing power cables both undersea and onshore, as well as an extension to the existing onshore Electrical substation to house the equipment needed for connection into the UK National Grid.

[13] The wind farm was officially inaugurated by the Secretary of State for Energy and Climate Change, Ed Davey on 30 October 2014.