[1] The total length is 2,727 feet (831 metres), and the vertical clearance at low river levels is 85 ft (26 m).
[6][7] Construction began in early 1968 and was completed on May 28, 1970, at a cost of $17.1 million; it was originally scheduled to open in December 1969.
[9] In 2009, the Oregon Department of Transportation spent $7 million to repave the roadway and replace the expansion joints on the bridge.
[4] In 2017, the Oregon Department of Transportation launched a project to widen I-205 to three lanes between the Abernethy Bridge and Stafford Road.
[10] Part of the proposed plan includes removing the Highway 43 to I-205 northbound on-ramp and widening the Abernethy Bridge.