It was opened on 30 April 2023 by the Victorian government as the first piece of public infrastructure delivered by the North East Link project.

The carpark is covered by a 5,000 square metre green roof, with walking and cycling paths connecting to Koonung Creek Trail and Thompsons Road.

[6] The facility has first been announced in November 2017 as a part of the North East Link project by the Minister for Public Transport, Jacinta Allan.

[8] Since construction started in 2021, some residents living next to the building site in Bulleen had their driveways blocked, causing hazards in case of an emergency.

Although they supported the project itself, they condemned the lack of consultation and bad planning by the North East Link program committee.