Construction of the Trans-Alaska Pipeline System

[4] In 1969, the unincorporated Trans-Alaska Pipeline System group drilled a series of core samples north of the Brooks Range that demonstrated how ubiquitous the permafrost was along the route.

To cross these with the pipeline, engineers designed concrete "jackets" to surround the pipe and weight it down so it would sink to the bottom of the stream or river.

Construction of the Dalton Highway started on April 29, and at the peak of the effort, Alyeska and the four subcontractors had more than 3,400 workers deployed from the Yukon River to Prudhoe Bay.

[18] On Section One, which ran 153 miles (246 km) from Valdez to the Sourdough pipeline camp, River Construction Corporation, a division of Morrison–Knudsen, was given the contract.

Together, the two sections covered 210 miles (340 km), and they both were under the supervision of Arctic Constructors, a venture of Brown & Root Inc., Ingram Corporation, Peter Kiewit Sons Inc., Williams Brothers Alaska, Inc., and H.B.

As air traffic increased, Alyeska arranged for the use of Fort Wainwright's airfield to relieve the burden on Fairbanks International Airport.

But then the welders from 798 starting cooking their own lunches (against camp rules) using steaks taken from the kitchen freezers on makeshift grills whose burners were their acetylene torches.

[43] Toward the end of the pipeline project, a series of bumper stickers was produced with the slogan "Happiness is 10,000 Okies going south with a Texan under each arm".

[46] There were frequent allegations of corruption by Teamsters on the project, and the Anchorage Daily News won a Pulitzer Prize for a 15-part series on the rise of Local 959 and its influence on state politics.

[45] Repeated allegations of links to organized crime were never backed up by evidence, but two Teamsters leaders were murdered in 1976 while investigating drug activity on the pipeline project.

After his attempts to get Alyeska to upgrade the road were rebuffed, Teamster leader Jesse Carr stopped all truck traffic in the state for four days of safety meetings.

Laborers, as they were commonly known, did most of the odd jobs on the project: digging trenches in areas inaccessible by heavy equipment, drilling holes for the pipeline's Vertical Support Members, spreading gravel, crushing rock, and moving supplies by hand.

[59] Life during the pipeline construction project was characterized by long hours, poor conditions, and limited entertainment compensated by excellent benefits and pay.

Television broadcasts were delayed two days because of the need to fly tapes from California,[63] and most workers had to develop their own forms of entertainment.

In the first years of the project, workers were regularly treated to prime rib, steak dinners, and other exotic fare due to a cost-plus contract between the food preparers and the subcontractors.

[65] In later years, these cost-plus contracts were replaced, and institutional cooking and box lunches became common, but the food on the project was still prized by many workers.

The International Brotherhood of Electrical Workers (IBEW) LU 1547 was one union that had overtime on Sundays changed from double time to time-and-one-half upon completion of the haul road.

[69] The large amounts of money in the pipeline camps and a lack of entertainment caused frequent gambling games that sometimes involved tens of thousands of dollars.

These crews were followed by another group of surveyors and engineers who determined whether the pipeline could be laid in the planned spot, or if it had to be moved because of permafrost, soft ground, or other considerations.

State and federal surveillance officers, working with the engineers, could give the OK to move the path of the pipeline as much as 200 feet to the right or left in order to avoid obstacles.

"[83] To take advantage of that "top effectiveness", Moolin set an ambitious goal for 1976 construction: "We're expecting to have all of the line installed, insulated, and hydro-tested by November 1", he said in January.

In September 1975, a former employee of Ketchbaw Industries filed suit against the company, alleging that he had been laid off because he would not participate in a conspiracy to falsify quality control X-rays of pipeline welds.

[89] The controversy continued, however, as Kelley's lawsuit moved forward, a Ketchbaw manager was found dead of cyanide poisoning, and photographs of welds were stolen from a pump station construction camp.

Then a team of 12 men and inspectors riding on wheeled sleds pulled by a modified John Deere lawnmower entered the pipe.

Because doing repair work would interfere with the migration of Arctic char, the Alaska Department of Fish and Game allowed only 24 hours for the project.

As they were completed, the pump stations received hydrostatic testing, in which portions of pipe were filled with water and subjected to pressures in excess of the eventual operating conditions.

[96] Because of loose soil found at the job site, enormous retaining walls had to be constructed to secure the ground below some of the 58 structures that were completed by the end of the year.

The oil emerging from wells at Prudhoe Bay was more than 120 °F (49 °C) degrees, and there was a danger that if it was introduced before intermediate warming, the pipeline could crack because of thermal expansion.

[102] The startup process and construction as a whole came to an end on August 1, 1977, when the tanker ARCO Juneau sailed out of Valdez with the first load of oil from the Trans-Alaska Pipeline System.

The increase, Alyeska reported, was due to material and freight costs, repairs needed to poorly built sections of pipeline, and contingency estimates.

Pipeline on slider supports where it crosses the Denali Fault .
Radiators atop heat pipes keep permafrost below the pipeline frozen.
Before construction of the Dalton Highway , special vehicles like the Sno-Freighter were needed to take supplies north of the Yukon River .
A map of the Trans-Alaska Pipeline with pump stations and construction camps identified.
The pipeline crosses the Tanana River on a bridge north of Delta Junction.
The pipeline runs under this riverbed, emerging to cross a ridge on the opposite bank. Pipeline inspection access road is visible as well
Etchings on a pipeline vertical support member indicates when a nearby weld was X-rayed by quality control inspectors.
The portion of the pipeline beneath the Sagavanirktok River , seen here, caused problems for construction workers.
Pump Station 9 as seen in 1994.
The E. L. Patton Yukon River Bridge was not completed until October 1979.