Drax Power Station

Drax was initially conceived by the Central Electricity Generating Board (CEGB) in 1962 as the country's largest power station thus far, at about 3,000 MW.

[10][9] Authority to carry out preparatory works was granted in December 1964, leading to full permission in March 1966, on the basis that the station would be designed to accommodate six 660 MW units, but that only the first three be proceeded with for the time being.

The Board decided in 1977 that construction of the final three units would commence in 1979 with the target of commissioning in 1985/6, as part of meeting load growth with an adjusted mix policy aiming for a balance of coal, nuclear, and oil.

However, later that year in July, the Government requested that Drax Completion proceed immediately, ahead of requirements, in order to secure jobs in the North East's heavy manufacturing industries.

The architectural critic Reyner Banham was scathing of the design: 'less a brick cathedral than a concrete bunker... obsession with ribbed surfaces and forceful projections that have their origins in brutalism'.

[19] In 2009, Drax Group submitted a planning application for the 300 MW biomass Ouse Renewable Energy Plant next to the power station.

[21] In February 2012 the company ceased planning development of the plant, citing logistics costs, and uncertainty concerning government financial support for biomass.

[24] On 17 June 2009, Secretary of State for Energy and Climate Change Ed Miliband announced plans that would require all UK coal-fired power stations to be fitted with CCS technology by the early 2020s or face closure.

[29][30] In September 2015 Drax announced it would not be making any further investments into the CCS scheme after completion of the feasibility study because negative changes to government support for renewable energy had made the project too financially risky, plus drops in the company's share price due to the same uncertainty had reduced Drax's ability to raise funds.

As a result, Leigh Hackett, CEO of Capture Power stated that "[I]t is difficult to imagine its continuation in the absence of crucial government support".

[34][35] In May 2018, Drax announced a new carbon capture and storage pilot scheme that it would undertake in conjunction with the Leeds-based firm, C-Capture.

As the station was designed and constructed prior to the CEGB's commitment to Flue Gas Desulphurisation, extensive measures were made to limit acid attack from 'sulphurous condensate', namely the lining of the flues with a fluoroelastomer, and coating of the upper 29 m (95 ft) of the external surfaces with a mix of acid-resisting tiles and said fluoroelastomer.

[9] The twelve 114 m (374 ft) tall natural draft cooling towers stand in two groups of six to the north and south of the station.

[46][47] The main transport route to the power station for fuel (originally coal) is train via a 4.5-mile (7.2 km)-long freight-only section of the former Hull and Barnsley Railway, from the Pontefract Line at Hensall Junction.

In c.2007 GB Railfreight won a contract to move coal brought from the Port of Tyne, celebrated by the company naming one of their locomotives Drax Power Station in 2007.

[58] DB Cargo UK haul coal from the nearby ports of Hull and Immingham, and from Hunterston Terminal on the west coast of Scotland.

[68] In the 2000s Drax Group applied for planning permission to build a new 300 MW power station, fuelled entirely by biomass, to the north of the station; the Ouse Renewable Energy Plant was expected to burn 1,400,000 tonnes of biomass each year, saving 1,850,000 tonnes of CO2 emissions, and expected to create 850 construction jobs and 150 permanent jobs created once opened, through direct and contract employment.

[69] Plans were submitted to the Department of Energy and Climate Change in July 2009 for review; if permission was granted, construction was scheduled begin in late 2010 and to take up to three and a half years.

This is equivalent to two-thirds of Europe's entire energy biomass consumption in 2010, and requires 1,200,000 ha (4,600 sq mi; 12,000 km2) of forest to supply on a continuous basis.

[76] Drax Group's decision was enabled by a new UK government policy, effective in April 2013, to award 1.0 tradable ROCs (renewable obligation certificates) per megawatt of power generation from coal power plants that are fully converted to burn biomass; CEO Dorothy Thompson stated the company intended to become a predominately biomass-fuelled energy producer.

[90] In April 2014 Drax was awarded a renewable contract for difference (CFD) subsidy for biomass based power generation on another converted coal firing unit, but a third unit, which had been previously marked as eligible for CFD funding was excluded; Drax Group then legally challenged the decision, initially obtaining a ruling in its favour, which was overturned in the Court of Appeal.

[101] In December 2016 the European Competition Commission approved UK government subsidies for the conversion of the third unit to biomass burning.

[102][103] In 2024, Drax paid a penalty of £25 million to Ofgem after the regulator determined there was "an absence of adequate data governance and controls in place" regarding Canadian wood sources from April 2021 to March 2022.

[104] In February 2025, the UK government extended its operation from 2027 to 2031, but at a reduced 27% maximum load factor using 100% sustainable wood, so it would run "less than half as often as it currently does", generally only at times of high electricity demand.

The Environment Agency (EA) granted permission for the trial in June 2004, despite the plans being opposed by Friends of the Earth and Selby Council.

[64] The EA granted permission in early 2008 after agreeing with Drax's findings that the fuel had no significant negative effects on the environment.

[128] In 2007, in a move to try to lower CO2 emissions, Drax Group signed a £100 million contract with Siemens Power Generation to re-blade the steam turbines over four years.

[130] Drax remained the UK's largest single emitter of carbon dioxide up until 2016, when the power station claimed that its improvement programmes and conversion to burning biomass, had meant a drastic decrease in greenhouses gases being released into the atmosphere.

[134] At 8:00 am on 13 June 2008, more than 30 climate change campaigners halted an EWS coal train en route to the station by disguising themselves as rail workers by wearing high-visibility clothing and waving red flags.

They then mounted a banner reading "Leave it in the ground" on the side of the wagon and tied the train to the bridge, preventing it from moving.

The delivery of a Babcock steam drum during construction (1974)
A schematic diagram of the proposed pilot scheme at Drax power station to capture and store carbon dioxide emissions
Turbine hall (left: outside, right: inside) The taller light-coloured building behind is the boiler house
The rotary coal loader feeding the plant from the stockyard
The Goole straw pellet plant (2009)
Generator unit No. 2
Southern cooling towers seen across the River Ouse, which supplies water for the condensers
A train of gypsum heading from the station to Kirkby Thore on the Settle-Carlisle Railway
Drax power station is the largest CO 2 emitter in the UK. The cloud of water vapour emitted by the station is due to scrubber systems introducing moisture into the exhaust stream. Despite its visible density, it contains less pollutants than an invisible stream of unfiltered exhaust.
"Camp for Climate Action" (2006)