[3] The "Balance of Plant" civil engineering and site works for the wind farm was performed by Catcon for all three stages of construction.

[6] Before the whole wind farm was commissioned, Hornsdale was generating 86 MW immediately prior to the 2016 South Australian blackout in September 2016.

Jessica Turner is a Nukunu woman whose artwork represents the story of the serpent's role in forming aspects of the landscape, particularly waterholes.

Chris Angrave and Louise Brown are Ngadjuri people who depicted how the Mungiura were found in hilly country, peering over the top of windbreaks before a storm, and blowing hard, which caused a whirly wind.

[22] This easily beat Elon Musk's wager of "100 days from contract signature",[13][23][24] which started when a grid connection agreement was signed with ElectraNet on 29 September 2017.

Diagram of power and duration of the two sections of battery