[2] On 16 September 2019, the Jiaxing Municipal People's Government approved the construction plan of the tram for 2019–2023.
[6] On 5 November 2020, the first box substation of the first phase was moved to basis, and the leveling, installation, and connection of the equipment was completed.
[9] On the afternoon of 11 December, the beam and slab erection of the first bridge of the T1 line was completed.
This marked that the rail laying construction of the first phase had entered a comprehensive stage.
[10] In the same month, the Operations Control Center (OCC) completed the structural capping.