Kajang 2 railway station

According to the Managing Director of the MKH Berhad, Tan Sri Eddy Chen Lok Loi, the company had purchased 275 acres (111 ha) of land in Kajang 2 as early as 2003 and had proposed to the government to jointly develop 14 acres (5.7 ha) of railway reserve land through a smart partnership model.

[1][2] Eddy Chen also mentioned that the two-story Kajang 2 station is scheduled to be completed in March 2018.

MKH funded the construction of the station with RM33 million, and the entire development area covers 13 acres (5.3 ha).

[4] The construction cost of the station due to the pandemic-related factors, has exceeded the budget and reached RM70 million.

Two accessible lifts equivalent to three-storey in height will be installed at both ends of the pedestrian bridge.

In order to encourage nearby residents to use the new train station, the parking fee for the first month of opening will be free.