[3] Construction was delayed in July 2018 when unexploded ordnance was discovered on the site, left from historic military testing.
[5] The 212 MW wind farm reached full generation capacity in late April 2022.
Stage Two for the final 24 turbines received financial approval from Nexif Energy in December 2018.
[11] The wind farm substation was connected to the national electricity grid on 25 February 2019.
The energy storage battery was expected to be installed by the end of May 2019, with wind turbines commissioned from August 2019.