Line 6 Finch West

The line will operate in a dedicated above-ground right-of-way, much of it within Finch Avenue, segregated from street traffic.

[18] In April 2012, Metrolinx proposed to start construction on the Finch West LRT in 2015, with the line opening in 2018.

[13] By November 2012, when the city and province signed an LRT master agreement, construction for the line was to begin in 2015 for completion in 2020.

[19] In May 2017, Metrolinx confirmed that it had entered into an agreement with Alstom to build 17 (later revised to 18)[12] light rail vehicles for Line 6 Finch West.

[20] In September 2017, Metrolinx announced the line would not open until 2022 at the earliest, blaming the delay on uncertainty with the Bombardier vehicle supply.

[22][23][24] After consultation with Mosaic on a construction schedule, Metrolinx delayed projected completion of the line to 2023, ten years after the originally announced date.

[25] That May, Infrastructure Ontario and Metrolinx announced that Mosaic had signed a contract to design, build, and finance the construction of the line and stations, and to maintain them for 30 years after their initial opening.

[31][32] By late October 2020, the first rails were being installed at the line's new maintenance and storage facility,[33] with the first vehicles scheduled to arrive in mid-2021.

[29] In December 2020, Mosaic Transit Partners awarded Bombardier Transportation a 30-year contract to maintain Line 6's light-rail vehicles as well as wayside systems such as track and overhead catenary.

[29] In late January 2022, the first vehicle test on the Finch West LRT occurred at its maintenance and storage facility.

[35] In February 2022, an LRV made a 700-metre (2,300 ft) trip from the MSF along York Gate Boulevard onto Finch Avenue.

[35] By May 2022, Mosaic Transit Group had laid about 35 percent of the 25.6 kilometres (15.9 mi) of total track required to complete the line.

[40] By late June 2023, canopies have been fully or partially installed at Sentinel, Tobermory, Driftwood, Jane and Finch, Norfinch/Oakdale, Signet Arrow, Duncanwoods, Rowntree Mills, Stevenson, Albion, Martin Grove and Westmore stops.

[44] By mid-September 2024, construction had finished for the two terminal stations and all surface stops; the testing and commissioning phase remained to be completed.

Mosaic expected the TTC to "facilitate effective implementation of maintenance and operational requirements once the line commences service".

[11] In December 2023, the TTC made the assumption for budget purposes that Line 6 would open no earlier than September 2024.

[4] From west to east, the 10.3-kilometre (6.4 mi)[5] line will run from Humber Polytechnic's North Campus at Highway 27 in northern Etobicoke, using the college's former name of Humber College, to Finch West station on Line 1 Yonge–University, at Keele Street in North York.

Between the two terminals, there will be 16 on-street stops, all along Finch Avenue,[9] where tracks run in the middle of the street, segregated from traffic.

[12] From its western terminal, Humber College station, the line will run north in a trench along the west side of Highway 27 to its intersection with Finch Avenue, where the line will curve east in a short tunnel under the intersection and rise to street level along Finch Avenue.

[53][54] One block east of the Norfinch Oakdale stop, at York Gate Boulevard, there will be a wye junction to the line's maintenance and storage facility.

About 500 m (1,600 ft) east of the latter stop, opposite Romfield Lane, the line will descend into a tunnel under Keele Street to terminate inside Finch West station.

[60] Line 1 Yonge–University[66] TTC buses In January 2018, to avoid naming conflicts with existing TTC and GO stations in Toronto, a consultation process was initiated to select unique names for the stops at Jane, Kipling, Islington, and Weston; the initial suggestions were Jane and Finch, Mount Olive, Thistletown, and Emery Village, respectively.

[68] The line has been designed by Arup, DTAH and Perkins&Will – as part of the Mosaic Transit Group consortium.

This is to conform to crime prevention through environmental design (CPTED) standards to create a bright and safe environment for riders.

The turnback points from west to east are: Metrolinx has constructed a maintenance and storage facility (MSF) on a lot on the north side of Finch Avenue West between York Gate Boulevard and Norfinch Drive next to Monsignor Fraser College's Norfinch Campus.

The 100,000-square-metre (1,100,000 sq ft) site will include a maintenance building with an area of 10,000 square metres (110,000 sq ft),[12] open-air storage for up to 26 LRVs, a car wash facility, materials storage, an administration building and a traction power substation.

[76][73] In 2020, Metrolinx was criticized for proposing to sell off land in the Jane and Finch neighbourhood located in front of the MSF, contrary to initial promises to local community groups.

[77] A 32-metre-wide (105 ft) strip of land along Finch Avenue is currently being used as a construction staging area by Mosaic Transit Group.

In 2013, this plan was revived as an "unfunded future rapid transit project" in the City of Toronto's "Feeling Congested?"

With a forecast ridership of 6,600 in 2031 and a proposed line length of 6.3 kilometres (3.9 mi) along Finch Avenue West, the project scored "high" with a preliminary benefit–cost ratio of 0.36 to 0.65.

Finch West station on Line 1 Yonge–University will be the eastern terminus of the line
Rail and catenary pole installation at John Garland Boulevard in December 2022
Installed track slab in the section descending to Humber College station under construction in December 2022
Light rail portal descending into Finch West station under construction in March 2023
Mount Olive station in November 2023
Alstom Citadis Spirit vehicles used on Line 6 Finch West in 2023