[2] By the launch of traffic on the first diameter, weather modules or canopies, emergency call steles, benches, garbage cans and ticket windows for low mobility groups were installed on all platforms and stations.
[3] Major reconstruction within the framework of the MCD organization affected the platforms Khlebnikovo, Vodniki, Dolgoprudnaya, Novodachnaya [4] and Lobnya station.
[6] On April 13, 2019, construction of the Slavyansky Boulevard platform began, where a warm transition to the metro station of the same name is organized.
[10] In August 2019, construction of the passenger distribution hall (concourse) at the Setun stop began, where escalators and elevators will be installed and a barrier-free environment will be created.
[11] In April - October 2019, two additional platforms and four dead-end tracks for suburban electric trains departing from the station to the Smolensk direction were built at Belorussky railway station, which allowed to relieve the transit platforms.