A light rail system for Greater Manchester emerged from the failure of the 1970s Picc-Vic tunnel scheme to obtain central government funding.
[22] Expansion of Metrolink has been a critical strategy of transport planners in Greater Manchester, who have overseen its development in successive projects, known as Phases 1, 2, 3a, 3b, 2CC, and Trafford Park.
[25][26] The Greater Manchester Combined Authority has proposed numerous further expansions of the network, including the addition of tram-train technology to extend Metrolink services onto local heavy-rail lines.
After World War II, electric trolleybuses and motor buses began to be favoured by local authorities as a cheaper transport alternative, and by 1949 the last Manchester tram line was closed.
The project was a proposal to link Piccadilly and Victoria stations via a tunnel under the city centre and enable train services to run across the Manchester conurbation.
Light rail emerged in the early 1980s as a cost-effective option that could make use of existing railway lines and run through the city centre at street level, eliminating the need for costly tunnelling works.
[30] Initial abstract proposals, based on light rail systems in North America and continental Europe,[41] illustrated a draft 62-mile (100 km) network consisting of three lines: Altrincham–Hadfield/Glossop, Bury–Marple/Rose Hill and Rochdale–East Didsbury.
To promote the scheme, GMPTE held a public proof of concept demonstration in March 1987 using a Docklands Light Railway P86 train on a freight-only line adjacent to Debdale Park.
Because of the central government's constraints on financial support for innovative transport projects, funding was granted by HM Treasury with the strict condition that the system be constructed in phases.
[44][60] It was constructed 1997–99 by Altram (a consortium of Serco, Ansaldo and John Laing) and six new AnsaldoBreda T-68A trams were bought to operate services on the line, but were also used in other locations across the network.
[44][60][16] The line was inaugurated by Prime Minister Tony Blair on 6 December 1999[61] as far as Broadway tram stop as the street running section to Eccles Interchange was completed.
[62] The Phase 3 extension project, nicknamed the "Big Bang", was promoted by GMPTE and the Association of Greater Manchester Authorities (AGMA) in the early 2000s.
GMPTE and AGMA instead funded Phase 3b through a combination of council tax, government grants, Metrolink fares and contributions from the Manchester Airports Group and other bodies.
With increased tram traffic brought about by the expansion of the Metrolink network, it became necessary to build a new route across Manchester City Centre to alleviate congestion and improve capacity.
[87] The project also involved re-ordering St Peter's Square and re-siting the Cenotaph to accommodate an enlarged tram interchange and junction.
To protect the remaining underground burial vaults of the church, concrete slabs were put in place below street level before the tram tracks were laid.
[57][118][119][120] In December 2013, a further 10 M5000s were ordered to provide trams for the Trafford Park Line planned to open in 2020, while in the interim supporting a service between MediaCityUK and Manchester city centre and other capacity enhancements.
It was designed to assist with vehicle recovery and track and line repairs although to the end of its service life rarely left its base at Queens Road Depot.
[16] The T-68A vehicles were based on the original T-68s but had modifications replacing destination rollblinds with dot matrix displays, and retractable couplers and covered bogies necessary for the high proportion of on-street running close to motor traffic.
[137] In 2002, in the lead up to Manchester hosting the Commonwealth Games, a requirement to increase capacity for the event led to Metrolink investigating the purchase of redundant second-hand Boeing LRV vehicles from the Muni Metro system in San Francisco.
[149] Each stop has at least one high-floor platform measuring a minimum of 2 metres (6.6 ft) wide, accessed by ramp, stairs, escalator, lift or combination thereof.
[158] Constructed during Phase 1 alongside the Bury Line, it served jointly as a control centre, HQ, office space, and depot for the storage, maintenance and repair of vehicles.
[158] Consequently, Metrolink House was scaled down to a 4-hectare (9.9-acre) £8 million site with limited capacity,[158][159] and, in light of Phase 3a network expansion, the second depot in Old Trafford was built in 2011.
[160][147] This second depot, adjacent to the Old Trafford tram stop, occupies the site of a former warehouse and can stable up to 96 vehicles,[147] it also has a washing plant and maintenance workshops.
[161] On 7 May 2013 Metrolink completed the transfer of its main operational functions from Queens Road to Old Trafford, meaning its control room – known as the Network Management Centre – is housed jointly with the Customer Services team by its newer depot.
[188] Campaigners against the policy had argued that the ban on bicycles was anomalous, as other large objects such as ironing boards and deckchairs were allowed on the trams under current rules.
[207] A survey in 2012 revealed that passengers who used Metrolink every day for commuting rated service levels as poor and/or unreliable, with those respondents particularly frustrated by delays and disruptions.
[219] When the Metrolink network first came into operation in 1992, it used a system-wide colour scheme and vehicle livery of aquamarine, black and grey, along with a stylised "M" monogram placed at an angle within a circle.
[222][223] Before this, during the planning stage, the system was known as "Light Rapid Transit" (LRT) and promotional material used an orange and brown identity used by Greater Manchester Transport and GM Buses.
[235][236] In July 2022 the GMCA received confirmation of initial funding to develop the pathfinder, including the purchase of up to seven new tram-train vehicles to run the service.