The locks and their associated canal were the first major engineering project on the Ohio River, completed in 1830 as the Louisville and Portland Canal, designed to allow shipping traffic to navigate through the Falls of the Ohio.
From 1925 to 1927, the dam for generating hydroelectric power was added, and the locks were expanded, first by a private company and then by the U.S. Army Corps of Engineers.
At present, the normal pool elevation is 420 feet (130 m) above sea level and the drainage area above the dam is 91,170 square miles (236,000 km2).
The lock chambers are located at the dam on the Kentucky side of the Ohio River and are capable of a normal lift of 37 feet (11 m) between the McAlpine pool upstream and the Cannelton pool downstream.
The hydroelectric plant consists of eight turbine units with a net power generation capacity of 80,000 kilowatts.