Mesquite Solar project

The Mesquite Solar project is a 512.5-megawatt (MWAC) photovoltaic power plant in Arlington, Maricopa County, Arizona, owned by Sempra Generation and Consolidated Edison Development Inc.

The first three phases of the project were constructed using more than 2.1 million crystalline silicon solar panels made by Suntech Power.

Construction of Phase 1 over a 3.6 km2 site adjacent the Palo Verde Nuclear Generating Station began in 2011 and was completed in January 2013.

[3][4] It has a nameplate capacity of 150 megawatts (MW) that is contracted through a 20-year Power Purchase Agreement (PPA) with Pacific Gas and Electric Company (PG&E).

[6] Phase 1 cost about $600 million, is projected to generate more than 350 gigawatt-hours of electricity annually (an average of about 40 MW), and will offset roughly 200,000 tons of carbon emissions each year.

Mesquite Solar One (August 2012)