The NP Kunta Ultra Mega Solar Park, also known as Ananthapuram - I Ultra Mega Solar Park or Kadiri Ultra Mega Solar Park, is a solar park occupying a total area of 32 square kilometres (12 sq mi) in Nambulapulakunta mandal of Kadiri Constituency in Kadiri Division of Sri Sathya Sai district of the Indian state of Andhra Pradesh it is 35 km away from Kadiri.
The first phase of the park was commissioned on 9 May 2016 with a capacity of 200 MW.
A further 750 MW was planned to have been commissioned by March 2018 in the second phase.
In August 2016, Tata Power Solar commissioned a 100 MW solar project at the park built over an area of 200 hectares (500 acres).
In May 2018, Azure Power commissioned a 50 MW solar capacity at the park.