The original plans for the new stadium were scrapped in July 2015 by Japanese prime minister Shinzo Abe, who announced a rebid after a public outcry prompted by increased building costs.
[12] The new stadium will be the venue for athletics, rugby, some football games, and the opening and closing ceremonies of the Olympics and Paralympics.
[15] The roof of the new stadium was particularly problematic from an engineering perspective, as it required the construction of two steel arches 370 metres (1,210 ft) long.
As a result, Abe said that a replacement venue would have to be selected for the Rugby World Cup, as the new stadium would not be ready until the 2020 Olympics.
[19] Concern over indoor temperatures has also been raised, since, for cost reduction, Tokyo's New National Stadium was built without an air conditioner, and the roof was constructed over the spectator seating only.
It has been revealed that the athletics track will be a permanent feature not to be demolished for the additional 12,000 seats for any future World Cup bid.
[22] On 21 December 2015, the Japan Sport Council announced that Kuma and the Taisei Corporation had been selected to design and construct the National Olympic Stadium.
The new design would hold 68,089 in athletics mode with the ability to construct temporary seating over the permanent track to create an increased capacity of 80,016.
[24] Capacity during the Olympic Games was originally planned to 60,102 taking into account press and executive seating areas,along the broadcasting equipaments.
The stadium is unusual in that timber is used as a major component of the structure, all of it sourced from Japan in order to reduce environmental impact.
Part of the roof incorporates transparent solar panels and rain water is collected in underground cisterns and is used to irrigate the arena turf as well as the numerous plants on the top storey promenade.