NRLA

[4] A decision to fully complete the second tube of the Lötschberg Base Tunnel was made in early-2024, with an estimated cost of CHF 1.7 billion[5] and construction expected to extend from 2026 to 2033.

[6] During late-1980s and early-1990s negotiations with the European Economic Community (the predecessor of the EU), Switzerland demanded a limitation on transalpine truck traffic.

[8] The EU accepted the Swiss offer in 2000, but requested that the extant 28-tonne weight limit for lorries be raised to 48 tonnes.

The bilateral Land Transport Agreement with the European Union was signed, agreeing to an increase of the kilometer-based tax (HVF; German: LSVA, French: RPLP, Italian: TTPCP) on HGVs from 1.6 ct/tkm to 1.8 ct/tkm when the NRLA was completed.

[10] The original plans for the NRLA were to construct only one main base tunnel, but regional disputes prevented a choice between the two options and threatened to jeopardize the entire project.

The bilateral agreements with the EU containing the 40-tonne limit and the implementation of the HVF were finally accepted by the Swiss populace on 21 May 2000 with 67.2% support in a federal optional referendum initiated by opposing political parties.

The axis is the first flat trans-alpine rail link, with a maximum elevation of 550 metres (1,800 ft) above sea level.

It was formally opened in a ceremony the next day, during which the tunnel was conveyed to its operator: Swiss Federal Railways (SBB CFF FFS).

The 34.6-kilometre-long (21.5 mi) base tunnel opened to traffic on 7 December 2007; it was the first part of the NRLA to be delivered, but is only partially completed.

[24] The resulting plan was presented in Spring 2019, with options of either only fitting out the existing 14 km of unequipped tunnels or fully completing the second tube.

[6] That choice is naturally more expensive and will take two years longer, but it provides a much higher capacity and avoids fully closing the line for eight months.

Rail map of Switzerland and surrounding countries
The NRLA project is the centrepiece of the Central European rail network.
See caption
Three-way junction under construction in the Gotthard Base Tunnel in 2006
Called "the project of the century", the Gotthard Base Tunnel is the first flat route through any major mountain range, from the northern plains (here in Erstfeld ) to the southern plains. In the background here looms the majestic 3,073-metre-high (10,082 ft) Bristen mountain.