Obrigheim Nuclear Power Plant

In March 2017, EnBW tested the shipment of numerous castors by a barge on the Neckar to Neckarwestheim Nuclear Power Plant.

On May 5, 1955, the Federal Republic of Germany, with the French occupation force, started to work in earnest towards peaceful use of nuclear energy.

The minister-president and minister of the economics of Baden-Württemberg at the time, Hermann Veit took over the project of establishing a nuclear power plant, and looked towards the Calder Hall Gas cooled reactor in England for a design.

When the much smaller AEC demonstration facility at Piqua, Ohio suffered severe problems, they switched to a light water reactor in 1962.

[6] Since 2005 the EnBW owned nuclear power in Obrigheim has been in the process of decommissioning; the spent fuel rods have been in wet storage since 2007.

[7] For EnBW not to have to build one, the fuel rods needed to be shipped to the Neckarwestheim Nuclear Power Plant, which is about 40 kilometers away and still had space in its temporary storage.

[4][8] Since both nuclear plants were built on the banks of the Neckar, barge transport appeared to be the preferred way in spite of the 23 bridges and six locks it must pass.

The Obrigheim Nuclear Power Plant on the left
View of the nuclear power plant
The nuclear power plant in 1979