[3] According to Brian Windsor, an ODOT structural engineer, without redundant support, the failure of a single beam created the risk of total collapse of that section of bridge.
[5] Attention to the Crosstown project increased in August 2007 after the collapse of the I-35W Bridge over the Mississippi River in Minneapolis, Minnesota.
In an August 2007 poll sponsored by The Oklahoman, nearly 2⁄3 of respondents indicated that they were "afraid to drive across the Crosstown bridge in Oklahoma City".
Devon Energy announced in March 2008 it would construct a one million square foot office tower in the center of a revitalized downtown to house between 2,000 and 3,000 of its employees.
However, in May 2009 the final decision from the STB reversed the earlier ruling, allowing the ODOT to move ahead with their plans.
ODOT Director Gary Ridley said the then current I-40 will "absolutely" survive through 2012, the completion date for the realignment, adding, "If we felt there was anything wrong that would cause us concern, we would close it, and we wouldn't think twice about it.
"[12] However, in a filing with STB, Ridley urged a quick ruling because "new serious issues including cracks in fracture critical members are constantly being discovered and repaired.
Under the original Environmental Impact Statement, residents of two neighborhoods were to be displaced by construction of the new Crosstown Expressway.
On June 20, 2006, the Oklahoma City Council[33] announced a $387,000 contract for professional consulting services with the URS Corporation "to recommend specific actions to facilitate redevelopment within the area impacted by the relocation of the downtown section of I-40, Reno Avenue, new I-40 alignment, Western Avenue and I-35/I-235"[33] On October 5, 2006, Oklahoma City Mayor Mick Cornett introduced the 'Core to Shore' project team which has the task of "planning and developing the area south of downtown and north of the Oklahoma River where Interstate 40 currently runs.