In September 2008 the Minister of Defence announced delays in delivery of the two OPVs due to questions regarding the ships' seaboats and Lloyds Certification.
[3] NZ Ministry of Defence claimed the overweight issue was not as bad as previously thought, but "weight will have to be carefully monitored during the ship's life".
HMNZS Otago arrived at Devonport Naval Base after further delay in Australia due to engine problems, which were fixed under warranty.
The Government and Navy policy was the OPVs are intended to carry out resource protection functions in the EEZ, South Pacific and Southern Ocean, to free the two Anzac-class frigates for other needs.
In reality the ice-strengthened belt resulted in the OPVs being 300 tons overweight and required much time and $84 million expenditure to modify.
Also at issue was a third OPV[8] rather than the IPVs strongly backed by Ministry of Fisheries and Defence Minister, Phil Goff, which lacked military relevance other than reserve and command training.