In a statement in March 2023, the Ministry of Defence (MOD) said that full operating capability was expected between October 2028 and September 2029, when the army has trained and converted forces to the vehicle.
[9] Deliveries of production Ajax vehicles to frontline British Army units began in January 2025, some eight years behind the original schedule.
After the Ministry of Defence had selected the ASCOD 2 Common Base Platform, BAE tried to reverse the decision by offering to manufacture the CV90 at their Newcastle facility.
General Dynamics has conducted design review work using the input of soldiers and bringing the ASCOD 2 Chassis in line with the British requirements.
[citation needed] On 3 September 2014, the British Government ordered 589 Scout SV vehicles, totalling a cost of £3.5 billion excluding VAT.
[14] In July 2015, the Ministry of Defence concluded their study into having final assembly of the Scout SV vehicles take place in the UK rather than General Dynamics' primary production facility in Spain.
[16] Thales UK won the sight system contract for the Scout family, safeguarding engineering and manufacturing jobs at their site in Scotland.
The Scout SV is also equipped with a state of the art Intelligence, surveillance, target acquisition, and reconnaissance (ISTAR) package with advanced sensors and space for further future growth.
The Ajax has a 20 Gbit/s Ethernet intelligent open architecture, which enables it to capture, process and store six TBs of information gathered by the sensors.
Test crews were required to wear noise cancelling headphones and be checked for hearing loss at the end of operations and the vehicles were unable to reverse over obstacles more than 20 centimeters high.
[25] In June 2021 it was revealed that trials of Ajax variants were halted from November 2020 to March 2021 due to excessive vibration and noise, leaving crews suffering from nausea, swollen joints and tinnitus.
[28] In early 2021 MPs on the Defence Select Committee issued a report critical of the state of the Army's armoured vehicle programme—including Ajax—which had spent hundreds of millions of pounds with little to show for it.
The paper quoted Francis Tusa, editor of Defence Analysis, concluding that the British Army "are spending good money after bad for something that is arguably unfixable.
"[27] On 15 December 2021, Quin updated the Parliament and stated that "We are commissioning a senior legal figure to look more deeply at Ajax, and not just health and safety; to examine the cultural and process flaws that it has highlighted.
[30] In June 2022 a report by the UK Parliament's Public Accounts Committee found that delays had been caused by a "litany of failures" and advised that the Ministry of Defence needed to either resolve the problems or scrap the project, to prevent the compromising of national security.
"[34] In March 2023 the MOD said that it had resumed payments to General Dynamics Land Systems UK (GDLS-UK), having halted them more than two years previously.