Semmering Base Tunnel

[2] Construction began on 25 April 2012 and the link is expected to enter operational service in 2030,[3] delayed from the original estimate of 2026.

By the turn of the 21st century, a total of 70,000 goods and passenger trains were reportedly being run through the Semmering railway during each year, it is one of the busiest routes in Austria.

[9] Outside of railway infrastructure, a flood protection scheme is required to mitigate against the risk posed by the nearby River Schwarza while the relocation of the B27 [de] road would also be necessary.

[9][13] In June 2024, Porr and Rhomberg Sersa Rail Group were awarded a €176 million fit-out contract for the tunnel.

The central section is to consist of 26 crossover passages between the two tunnels, along with an emergency station; a pair of 420 metre-deep ventilation shafts are also to be dug.

[10][11] By 7 June 2016, work on the third section of the SBT had commenced; this meant that full-rate construction activity upon the project, which was reportedly costed at €3.3 billion as of this point in time, was now underway.

At Göstritz, a 1,000 metre access gallery and multiple 250 metre-deep shafts were constructed to facilitate conventional tunnel excavation methods.

[9] At Fröschnitzgraben, a pair of 420 metre-deep shafts, possessing a diameter of 22 metres, were dug ahead of the deployment of tunnel boring machines.

[18] Additional major works will include the construction of entrances in Gloggnitz and Mürzzuschlag, as well as ventilation shafts at Trattenbach and Sommerau.

Route map
Route map
Northern tunnel portal at Gloggnitz (2019)