[2] It is located at the underground of the junction of Huanhua Road (浣花路) and Fangcun Avenue East (芳村大道东) in Fangcun, Liwan District, Guangzhou.
Exit B was opened on 25 June 2019 and temporarily closed between 13 August 2022 and 27 December 2024 to accommodate the construction of the Line 11 station.
At the same time, after the opening of the station of Line 11, new exits D and E were added.
The construction of the Guangfo line station started on 24 September 2009, and the main structure was topped out on 14 January 2013.
[11] In order to facilitate the connection to the station part of Line 11, on the eve of the opening of Line 11, the north part of the paid area of the Guangfo line concourse was redivided, the number and location of the turnstiles at the interface connecting to the Line 11 station were adjusted, and the elevators originally divided into the connecting platforms outside the paid area were included in the paid area.