Plans were submitted to Harborough District Council in February 2014, with the intention to begin construction to be ready for the September 2014 cohort.

[citation needed] The Kier Group were contracted for the project with a build programme beginning on 9 February 2015 and finishing with a final handover on 27 November 2015.

Due to delays with planning permission, the build didn't start until 27 March 2015.

The first intake of students were admitted in September 2014[5] and as a result of the building not being completed, a temporary building was erected on the Lutterworth College site to accommodate the students until construction on the school was complete.