A3 (Albania)

The motorway starts at the TEG Shopping Center interchange connection with Tirana's Outer Ring in Lundër near Sauk south of the Grand Park of Tirana, and follows a route parallel to the National Road 3 (SH3) on the Erzen Valley until the village of Krrabë.

Close to the border between the counties of Tirana and Elbasan, the motorway passes along the Krraba tunnel.

Passing the tunnel, the highway continues within the Kusha Valley towards Elbasan, where it meets the SH3 again at Bradashesh where the motorway ends.

According to the former Minister of Transportation and Infrastructure, Sokol Olldashi, the construction of the Tirana bypass or outer ring began in March 2011.

The end of construction for the entire route from Tirana to Elbasan was projected for June 2013 (18 months construction time), however a hill collapse near Ibe further delayed completion due to inadequate geological feasibility studies.