Barsingar power station project is a 250-megawatt (MW) lignite based power station operated by NLC India Limited, formerly Neyveli Lignite Corporation (NLC), located at Barsingsar in Bikaner district, Rajasthan, India.
[1] Lignite for the power project is being supplied from the Barsingsar Mine, which is owned and operated by NLC.
[2] The company was subject to a financial crunch as a result of delays in commissioning the plant.
[3] In its July 2010 annual report, NLC stated that the second unit was scheduled to be commissioned in September 2010,[2] but the second 125 MW was commissioned on 25 January 2011,[1] and a media report in late 2011 stated that "the modification works for the second unit are progressing very slowly."
The media report also said the station contractor BHEL was "failing to keep its commitment that it will commence commercial operations of the Barsingar thermal power project by end of September 2011."